Help to prepare safety case reports
This information is for Accountable Persons (APs) of high-rise buildings to assist them in preparing safety case reports for Building Assessment Certificates that include new cracking.
Cracks in walls or concrete are common. They do not necessarily mean that there are structural problems with the building.
However, new cracks should be investigated and may need to be monitored.
Scenario
New cracking has been noticed or reported in the building.
This might be as part of routine inspections of the building or it may have been reported by a resident.
Background and possible reasons
There are a number of possible causes for cracking. These include cracking could:
- be cosmetic or a local, non-structural issue
- indicate a structural problem
- be one example of a wider problem
Short term responses
The first thing to do is for someone competent to make an initial assessment as soon as possible.
This might be one of your staff if they have the necessary skills and experience. Width of cracks will be a relevant factor.
This should include looking for other cracking in the same or similar areas.
If the competent person is sure cracking is just cosmetic, you may not need to take any further action.
If you cannot be sure the cracking is just cosmetic, you will need to do more:
- arrange for a specialist to assess the cracking
- act on the assessment
- consider whether any urgent action is needed
- while this is unlikely if the cracking is new and limited, it should be considered
Additional responses
There are a number of possible outcomes after the cracking has been assessed.
These include:
- the specialist may recommend no further action
- they may recommend a programme of monitoring
- you may need to take action to put problems identified right
- what you need to do will depend on what the problem is, what caused it and how widespread it is
- if the problem is widespread, you may need to investigate further
Whatever the outcome, you should record details of the cracking and what you have done about it.
Ongoing management
Make sure you have a system in place for reporting and investigating possible building safety issues such as cracking.
If you need a programme of monitoring, put the arrangements in place to carry it out and to deal with any findings.
Other practical examples
- Internal
- Resident engagement
- Structural
Other useful information
- Safety case report – GOV UK guidance
- Preparing a resident engagement strategy – GOV UK guidance
- Fire safety in purpose-built blocks of flats
- Safety in high-rise residential buildings: accountable persons – GOV UK guidance
- BSR to introduce more proportionate and targeted approach for higher-risk building assessments – GOV.UK